ATTENDANCE
In-Person:
- Tim Bene
- Jay Phelps
- Bob Karnaugh
- Max Holthaus
- Paul Morely
- Art Givens
- Nick Silva
- Kevin Oliver
- Charlie Procter
- Mathew Baldwin
- Julio Sumarriva
- Chris Marlow
- Jacob Eggleston
On-Call Attendees:
- David Kessinger
Proxies:
Attendee / Proxy For: N/A
Action Items:
- Bridgeport core change Motor
- Hass parts ordered & working on solutions for chip catching
- Chair election next month
- Shop lights
- Stocking issues on existing models we use
- May be under warranty.
- Tim was planning on calling the 1000bulbs.com salesperson however the costs of basic lights on their website is so low
- $450 donation to Machine Shop – not yet showing up on our books
Review Prior Action Items:
N/A
Upcoming class commitments (and needs/carry-overs):
- What classes exist today? What gaps?
- Moodle – Bridgeport
- Tormach is a month away
- Plastics – Shapeoko 3 XXL
- Plastics – Formlabs
- Mastercam class
- Kevin offered to create Lathe and Mill classes
Tool Issues:
- Pasma Mill
- Making an odd noise at certain quill locations
- Possibly a drawbar issue
- Colchester Lathe
- cooling pump may be not working or low coolant
For Purchase:
- $-136 Machine Shop balance (possible accounting issue)
Discussion:
- Possible use of the newly approved powered floor cleaner
- Ongoing use of the 3 mills – one does not have a powered drawbar
- Tim is trying to come up with an option to support “crowdfunding” for potential new tools
- e.g. a 4 axis mill
- this would not be based on commitments to fund, it would be actual funds already donated in a separate account of some kind vs a DMS earmark approach
- Suggestion (David) – use a time limit (e.g. 18 months) and if exceeded funds are returned
- This is a complex issue to work out
- 4 axis mill pro’s and con’s
- Master Cam – not yet installed – we need Infrastructure to order a new PC that will support it
- Possibly selling the Millsport mill
- provides more funds for use
- more floor space
- Discussed pros and cons of Moodle
- Art went over the recent updates to Honorarium handling and limits
- Copyright assignment is automatic when you create a new class
- Tim procured more safety glasses
- Open house next month is the same time as the Machine Shop meeting
- Closed toe shows and safety glasses are required
- We have plastic panels for people to stand outside safely
Votes:
- Proposal to spend up to $500 on 5000 kelvin lighting – passed (unanimous, no abstentions)
Meeting adjourned